Franklin Distillery

Fairfield, CA

Contract Price
$4,800,000

General Contractor
San Jose Construction

Features
260,00sf tilt up with a two-week schedule from start to finish. Slab on grade is strategically reinforced slab using PNA dowel baskets at the saw cut joints and diamond dowel at the construction joints. Urata erected 97 panels within an 8 week duration. Outside the building we are performing cast-in-place screen walls, truck scale pit and seat walls. Our ability and track record for completing fast track projects was a major factor when being awarded the project.